NPRR #897 · Revision Request
NPRR897 Adjustments to Black Start Service (BSS) Procurement Timeline and Testing
ReasonMarket efficiencies or enhancements
Created2018-09-13
Approved2018-12-11
Sections Affected
3.14.28.1.1.2.1.522 Attachment M (new)
Summary
This Nodal Protocol Revision Request (NPRR) adjusts the timeline for the Black Start Service (BSS) procurement and testing process, adds a weather limitation disclosure form, and aligns the Load-Carrying Test procedure with actual practice.
Timeline
- Aug 29 '18
-
Sep 13 '18
PRS PRS MeetingPRSDeferred/Tabled Tabled Referred → ROS“to table NPRR897 and refer the issue to ROS” — Passed→ Language Consideration
- Oct 11 '18
-
Oct 18 '18
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Amended by the Oct 15 '18 ROS comments“to recommend approval of NPRR897 as amended by the 10/15/18 ROS comments as revised by PRS” — Passed→ Impact Analysis Consideration
-
Nov 15 '18
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC“to endorse and forward to TAC the 10/18/18 PRS Report and Impact Analysis for NPRR897” — Passed→ Revision Request Consideration
-
Nov 29 '18
TAC TAC MeetingTACRecommended for Approval Recommended for approval“to recommend approval of NPRR897 as recommended by PRS in the 11/15/18 PRS Report, with a proposed effective date of upon ERCOT Board approval” — Passed→ Revision Request Consideration
-
Dec 11 '18
BOARD Board of Directors MeetingBOARDApproved Approved“to approve NPRR897 as recommended by TAC in the 11/29/18 TAC Report” — Passed