NPRR #896 · Revision Request
NPRR896 Reliability Must-Run and Must-Run Alternative Evaluation Process
ReasonMarket efficiencies or enhancements / Regulatory requirements
Created2018-09-13
Approved2019-06-11
Sections Affected
3.14.13.14.1.2and 3.14.1.5
Summary
This Nodal Protocol Revision Request (NPRR) outlines the process ERCOT will use to evaluate the cost-effectiveness of procuring Reliability Must-Run (RMR) Service or one or more Must-Run Alternatives (MRAs).
Timeline
- Aug 29 '18
-
Sep 13 '18
PRS PRS MeetingPRSDeferred/Tabled Tabled Referred → ROS Referred → WMS“To table NPRR896 and refer the issue to ROS and WMS” — Passed→ PRS for consideration
- Sep 24 '18
-
Oct 10 '18
Listed without action at 1 meeting
- Oct 11 '18
- Oct 15 '18
-
Oct 18 '18
Listed without action at 12 meetings (Oct 18 '18 – Feb 6 '19)
- Feb 7 '19
-
Feb 14 '19
Listed without action at 3 meetings (Feb 14 '19 – Mar 7 '19)
-
Mar 14 '19
PRS PRS MeetingPRSRecommended for Approval Recommended for approval“To recommend approval of NPRR896 as submitted” — Passed→ PRS for Impact Analysis review
-
Apr 11 '19
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC“To endorse and forward to TAC the 3/14/19 PRS Report and Impact Analysis for NPRR896” — Passed→ TAC for consideration
-
May 22 '19
TAC TAC MeetingTACRecommended for Approval Recommended for approval“To recommend approval of NPRR896 as recommended by PRS in the 4/11/19 PRS Report” — Passed→ Board for consideration
-
Jun 11 '19
BOARD Board of Directors MeetingBOARDApproved Approved“To approve NPRR896 as recommended by TAC in the 5/22/19 TAC Report” — Passed