NPRR #886 · Revision Request
NPRR886 Agreements Between ERCOT and Other Control Area Operators
ReasonAdministrative
Created2018-08-16
Approved2019-02-12
Sections Affected
3.23 (new)
Summary
This Nodal Protocol Revision Request (NPRR) requires that ERCOT, to the extent possible, provide Notice and allow time for comments prior to executing any new or amended agreement with another Control Area Operator.
Timeline
- Jul 13 '18
- Aug 16 '18
- Sep 13 '18
- Oct 18 '18
-
Nov 15 '18
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Amended by the Oct 15 '18 ERCOT comments“To recommend approval of NPRR886 as amended by the 10/15/18 ERCOT comments as revised by PRS” — Passed→ PRS for Impact Analysis review
-
Dec 13 '18
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC“To endorse and forward to TAC the 11/15/18 PRS Report as revised by PRS and Impact Analysis for NPRR886” — Passed→ TAC for consideration
-
Jan 30 '19
TAC TAC MeetingTACRecommended for Approval Recommended for approval“To recommend approval of NPRR886 as recommended by PRS in the 12/13/18 PRS Report” — Passed→ Board for consideration
-
Feb 12 '19
BOARD Board of Directors MeetingBOARDApproved Approved“To approve NPRR886 as recommended by TAC in the 1/30/19 TAC Report” — Passed
-
—