NPRR #879 · Revision Request
NPRR879 SCED Base Point, Base Point Deviation, and Performance Evaluation Changes for IRRs that Carry Ancillary Services
ReasonAddresses current operational issues
Created2018-06-14
Approved2018-12-11
Sections Affected
6.5.7.26.6.5.1.1.16.6.5.1.1.26.6.5.1.1.36.6.5.1.1.46.6.5.2and 8.1.1.4.1
Summary
This Nodal Protocol Revision Request (NPRR) proposes that Intermittent Renewable Resources (IRRs) carrying Ancillary Service Resource Responsibilities receive a Security-Constrained Economic Dispatch (SCED) Base Point calculated using the five-minute intra-hour forecast of the Resource. Generation Resource Energy Deployment Performance (GREDP) metrics are added to score performance during these intervals. Base Point Deviation Charges are adjusted to treat IRRs providing Ancillary Services the same as conventional generators. These changes cannot be done manually and will be active once a system change is implemented. This NPRR contains clean-up changes to correct the unit of measure for some billing determinants, and an as-built correction to the Settlement equation in paragraph (4) of Section 6.6.5.2. These clean-up changes do not introduce any system impact or Settlement changes. This NPRR also contains administrative edits to paragraphs (7) - (9) of Section 8.1.1.4.1, to align the paragraph numbering with current Protocol formatting style. These edits are authored as “ERCOT Market Rules” in this NPRR.
Timeline
- May 30 '18
-
Jun 14 '18
PRS PRS MeetingPRSDeferred/Tabled Tabled Referred → WMS Referred → ROS“To table NPRR879 and refer the issue to WMS and ROS.” — Passed→ Language Consideration
-
Jul 11 '18
Listed without action at 1 meeting
- Jul 12 '18
- Jul 17 '18
-
Jul 19 '18
Listed without action at 1 meeting
- Aug 8 '18
- Aug 9 '18
-
Aug 13 '18
Listed without action at 4 meetings (Aug 13 '18 – Sep 5 '18)
-
Sep 13 '18
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Amended by the Aug 3 '18 ERCOT comments“To recommend approval of NPRR879 as amended by the 8/3/18 ERCOT comments as revised by PRS” — Passed→ PRS for Impact Analysis review
-
Oct 18 '18
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC Amended by the Sep 25 '18 ERCOT comments priority 2020 · rank 2800“To endorse and forward to TAC the 9/13/18 PRS Report as amended by the 9/25/18 ERCOT comments and the Revised Impact Analysis for NPRR879 with a recommended priority of 2020 and rank of 2800” — Passed→ TAC for consideration
-
Nov 29 '18
TAC TAC MeetingTACRecommended for Approval Recommended for approval“To recommend approval of NPRR879 as recommended by PRS in the 10/18/18 PRS Report” — Passed→ Board for consideration
-
Dec 11 '18
BOARD Board of Directors MeetingBOARDApproved Approved“To approve NPRR879 as recommended by TAC in the 11/29/18 TAC Report” — Passed