NPRR #877 · Revision Request
NPRR877 Use of Actual Interval Data for IDR ESI IDs for Initial Settlement
ReasonMarket efficiencies or enhancements
Created2018-06-14
Approved2018-08-07
Sections Affected
18.6.1
Summary
This Nodal Protocol Revision Request (NPRR) provides a process to allow for the use of actual metered interval data for initial settlement of an Operating Day for Electric Service Identifiers (ESI IDs) that currently require BUSIDRRQ Load Profiles. Currently, meter data is sent monthly on the 867_03 for ESI IDs with BUSIDRRQ Load Profiles, so most of the data used for initial settlement for these ESI IDs is estimated using proxy day data. The ESI IDs are resettled with actual data during final Settlement on the 55th day following the Operating Day. The result is inaccurate initial Settlement.
Timeline
- May 17 '18
- Jun 5 '18
-
Jun 14 '18
PRS PRS MeetingPRSRecommended for Approval Recommended for approval“to recommend approval of NPRR877 as submitted” — Passed→ Impact Analysis Consideration
-
Jul 19 '18
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC priority 2018 · rank 2290 priority 2019 · rank 2540“to endorse and forward to TAC the 6/14/18 PRS Report and Impact Analysis for NPRR877 with a recommended priority of 2018 and rank of 2290 for Phase 1 and a recommended priority of 2019 and rank of 2540 for Phase 2” — Passed→ Revision Request Consideration
-
Jul 26 '18
TAC TAC MeetingTACRecommended for Approval Recommended for approval Amended by the Jul 24 '18 ERCOT comments“to recommend approval of NPRR877 as recommended by PRS in the 7/19/18 PRS Report and as amended by the 7/24/18 ERCOT comments” — Passed→ Revision Request Consideration
-
Aug 7 '18
BOARD Board of Directors MeetingBOARDApproved Approved“approved NPRR877 as recommended by TAC in the 7/26/18 TAC Report” — Passed
- Feb 4 '20