ERCOT·WATCH Search ercot.com  ⌕
NPRR #854 · Revision Request

NPRR854  NOIE TDSP Submittal of Meters with Bidirectional Flow Caused by Generation Interconnected at Distribution Voltage

Approved sponsor South Texas Electric Coop., Inc. (STEC) posted 2017-11-14 ercot.com
ReasonMarket efficiencies or enhancements
Created2017-12-14
Approved2018-04-10
Sections Affected
10.2.210.2.3
Summary
This Nodal Protocol Revision Request (NPRR) removes the ERCOT Polled Settlement (EPS) Meter requirement for Non Opt-In Entity (NOIE) points of delivery that realize bi-directional flows as a result of generation that is interconnected to the Distribution System. NOIE Transmission and/or Distribution Service Providers (TDSPs) would assume the responsibility for supplying ERCOT with this meter data.
Timeline