NPRR #851 · Revision Request

NPRR851  Procedure for Managing Disconnections for Bidirectional Electrical Connections at Transmission Level Voltages

Approved sponsor Golden Spread Electric Coop, Inc. (GSEC) posted 2017-10-25 ercot.com
ReasonRegulatory Requirements
Created2017-11-09
Approved2018-06-12
Sections Affected
2.13.1.5.1
Summary
This Nodal Protocol Revision Request (NPRR) was developed to fully implement the market design envisioned in NPRR 596, External Load Serving Entities. This NPRR establishes a clearly defined disconnection process within ERCOT market rules applicable to a transmission voltage connection to the ERCOT grid which utilizes one electrical connection for both generation and load services.