NPRR #832 · Revision Request
NPRR832 Disallow PTP Obligation Bids and DAM Energy Bids that Sink at Private Use Network Settlement Points Without a Load Distribution Factor
ReasonAddresses current operational issues. Prevents unnecessary harm to Market Participants
Created2017-06-15
Sections Affected
4.4.6.14.4.6.24.4.9.6.1and 4.4.9.6.2
Summary
This Nodal Protocol Revision Request (NPRR) disallows Point To Point (PTP) Obligation bids and Day-Ahead Market (DAM) Energy Bids that sink at Private Use Network Settlement Points if the Day-Ahead Updated Network Model has not utilized a rational Load distribution factor for the Private Use Network Settlement Point.
Timeline
- May 10 '17
- May 11 '17
-
Jun 5 '17
Listed without action at 3 meetings (Jun 5 '17 – Jun 7 '17)
-
Jun 15 '17
PRS PRS MeetingPRSDeferred/Tabled Urgent status Tabled Referred → WMS“To grant NPRR832 Urgent status; to table NPRR832 for one month and refer the issue to WMS” — Passed→ PRS for consideration
- Jul 12 '17
-
Jul 20 '17
PRS PRS MeetingPRSDeferred/Tabled Tabled“To table NPRR832 until November 2017” — Passed→ PRS for consideration
-
Jul 31 '17
Listed without action at 9 meetings (Jul 31 '17 – Nov 1 '17)
- Nov 9 '17
- Dec 14 '17
-
Jan 10 '18
Listed without action at 8 meetings (Jan 10 '18 – Mar 19 '18)
- Apr 4 '18
-
Apr 12 '18
Listed without action at 1 meeting