NPRR #812 · Revision Request
NPRR812 Alignment of Currently Published Reports
ReasonMeets Strategic goals; Administrative
Created2017-01-19
Approved2017-04-04
Sections Affected
3.2.33.2.55.1
Summary
This Nodal Protocol Revision Request (NPRR) clarifies language related to short-term system adequacy reports, aligns Protocol language with current ERCOT practices and Public Utility Commission of Texas (PUCT) rules regarding the posting of Resource and Load information, and modifies the Protocol requirement to post a Reliability Unit Commitment (RUC) initial conditions report to only include the Hourly RUC (HRUC) process as originally intended in NPRR314, Requirement to Post Generation Resources Temporal Constraints.
Timeline
- Jan 4 '17
-
Jan 19 '17
PRS PRS MeetingPRSRecommended for Approval Recommended for approval“To recommend approval of NPRR812 as revised by PRS.” — Passed→ Impact Analysis Consideration
-
Feb 9 '17
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC priority 2017 · rank 1950“To endorse and forward to TAC the 1/19/17 PRS Report and the Impact Analysis for NPRR812 with a recommended priority of 2017 and a rank of 1950.” — Passed→ Revision Request Consideration
-
Mar 23 '17
TAC TAC MeetingTACRecommended for Approval Recommended for approval“To recommend approval of NPRR812 as recommended by PRS in the 2/9/17 PRS Report.” — Passed→ Revision Request Consideration
-
Apr 4 '17
BOARD Board of Directors MeetingBOARDApproved Approved“To approve NPRR812 as recommended by TAC in the 3/23/17 TAC Report.” — Passed
-
—