NPRR #799 · Revision Request
NPRR799 Updates to Outages of Transmission Facilities
ReasonMarket efficiencies or enhancements
Created2016-09-15
Approved2017-04-04
Sections Affected
3.1.23.1.5.13
Summary
This Nodal Protocol Revision Request (NPRR) introduces requirements for submitting updates to the Outage Scheduler for completed or started Outages on Transmission Facilities.
Timeline
- Aug 25 '16
-
Sep 15 '16
PRS PRS MeetingPRSDeferred/Tabled Tabled Referred → ROS Referred → WMS“To table NPRR799 and refer the issue to ROS and WMS.” — Passed→ Language Consideration
- Oct 6 '16
-
Oct 13 '16
Listed without action at 2 meetings (Oct 13 '16 – Oct 17 '16)
- Oct 20 '16
-
Nov 2 '16
Listed without action at 2 meetings (Nov 2 '16 – Nov 3 '16)
- Nov 10 '16
-
Nov 14 '16
Listed without action at 2 meetings (Nov 14 '16 – Nov 17 '16)
- Dec 1 '16
-
Dec 16 '16
Listed without action at 3 meetings (Dec 16 '16 – Jan 12 '17)
- Jan 13 '17
-
Jan 19 '17
PRS PRS MeetingPRSDeferred/Tabled Tabled“To table NPRR799 for one month.” — Passed→ Language Consideration
- Jan 30 '17
-
Feb 1 '17
Listed without action at 1 meeting
-
Feb 9 '17
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Amended by the Jan 19 '17 Morgan Stanley comments“To recommend approval of NPRR799 as amended by the 1/19/17 Morgan Stanley comments.” — Passed→ Impact Analysis Consideration
-
Mar 9 '17
PRS PRS MeetingPRSRecommended for Approval Forwarded → TAC“To forward to TAC the 2/9/17 PRS Report and the Impact Analysis for NPRR799” — Passed→ Revision Request Consideration
-
Mar 23 '17
TAC TAC MeetingTACRecommended for Approval Recommended for approval“To recommend approval of NPRR799 as recommended by PRS in the 3/9/17 PRS Report.” — Passed→ Revision Request Consideration
-
Apr 4 '17
BOARD Board of Directors MeetingBOARDApproved Approved“Approved NPRR799 as recommended by TAC in the 3/23/17 TAC Report.” — Passed
-
—
Posted since the last meeting