NPRR #795 · Revision Request
NPRR795 Provisions for Refunds of Capital Contributions Made in Connection with an RMR Agreement
ReasonMarket efficiencies or enhancements
Created2016-08-11
Approved2016-10-11
Sections Affected
3.14.1.15 (new) and 6.6.6.6 (new)
Summary
This Nodal Protocol Revision Request (NPRR) creates a mechanism by which capital expenditures funded by ERCOT under a Reliability Must-Run (RMR) Agreement may be refunded subsequent to the termination of the RMR Agreement. If the Generation Resource returns to commercial operations, the refund is based on depreciated book value of the capitalized expenditures. Otherwise the refund is based on the salvage value associated with the capitalized expenditures. This is similar to refunds of capital contributions that may be required for capacity procured under the provisions of Section 6.5.1.1, ERCOT Control Area Authority.
Timeline
- Aug 2 '16
-
Aug 11 '16
PRS PRS MeetingPRSDeferred/Tabled Urgent status Tabled Referred → WMS“To grant NPRR795 Urgent status; to table NPRR795 and refer the issue to WMS” — Passed→ PRS for consideration
- Sep 7 '16
- Sep 8 '16
-
Sep 15 '16
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Amended by the Sep 12 '16 Reliant comments Forwarded → TAC“To recommend approval of NPRR795 as amended by the 9/12/16 Reliant comments with a recommended effective date of October 12, 2016; and to forward the Impact Analysis to TAC” — Passed→ TAC for consideration
- Sep 21 '16
-
Sep 29 '16
TAC TAC MeetingTACRecommended for Approval Recommended for approval Amended by the Sep 28 '16 TIEC comments“To recommend approval of NPRR795 as recommended by PRS in the 9/15/16 PRS Report as amended by the 9/28/16 TIEC comments and revised by TAC” — Passed→ Board for consideration
-
Oct 11 '16
BOARD Board of Directors MeetingBOARDApproved Recommended for approval“To approve NPRR795 as recommended by TAC in the 9/29/16 TAC Report” — Passed
-
—
Posted since the last meeting