NPRR789  Publish All Mid-Term Load Forecast Results

Approved sponsor Citigroup Energy, Inc. posted 2016-07-08 ercot.com
ReasonAddresses current operational issues; meets strategic goals; market efficiency/enhancement
Created2016-08-11
Approved2016-10-11
Sections Affected
6.3.2
Summary
ERCOT has several Mid-Term Load Forecasts (MTLFs) per Weather Zone, but only one at a time is published for consumption by Market Participants. That published forecast can vary from hour to hour based on the model selected by ERCOT Operations. This Nodal Protocol Revision Request (NPRR) publishes the results of all of ERCOT’s MTLFs, as well as indicating which forecast is currently in use by ERCOT Operations.