NPRR #782 · Revision Request
NPRR782 Settlement of Infeasible Ancillary Services Due to Transmission Constraints
ReasonAddresses current operational issues; market efficiency/enhancement
Created2016-06-16
Approved2016-10-11
Sections Affected
4.4.7.45.5.26.4.76.4.9.16.4.9.1.26.4.9.1.36.4.9.26.4.9.2.36.7.2.1 (new)6.7.49.5.3
Summary
This Nodal Protocol Revision Request (NPRR) removes inconsistencies in Protocol language with a proposed change to the equations governing the Settlement of Ancillary Services for Resources that are not able to deliver on their Ancillary Service responsibilities due to transmission constraints. ERCOT collaborated with members of the Wholesale Market Subcommittee (WMS) and Qualified Scheduling Entity (QSE) Managers Working Group (QMWG) to address the inconsistencies in the Protocols and develop a proposal for the Settlement of infeasible Ancillary Services due to transmission constraints. ERCOT has drafted an NPRR based on the following Settlement principles: 1) The QSE with the infeasible Ancillary Service(s) will be charged the Day-Ahead Market (DAM) clearing price regardless whether the responsibility was awarded, self-arranged, or traded, and regardless of whether a Supplemental Ancillary Service Market (SASM) is executed. 2) The Ancillary Service replacement cost, if any, is charged to all QSEs based on the current Settlement allocation (Load Ratio Share (LRS) less self-arranged). 3) The QSE with the Ancillary Service infeasibility is not directly charged the full replacement cost, if any. 4) All revenues collected from charges to QSEs due to infeasible Ancillary Service(s) are paid to all QSEs based on the current Settlement allocation (LRS less self-arranged).
Timeline
- Jun 1 '16
-
Jun 8 '16
Listed without action at 1 meeting
-
Jun 16 '16
PRS PRS MeetingPRSDeferred/Tabled Tabled Referred → WMS“To table NPRR782 and refer the issue to WMS” — Passed→ PRS for consideration
- Jul 6 '16
-
Jul 14 '16
PRS PRS MeetingPRSRecommended for Approval Recommended for approval“To recommend approval of NPRR782 as submitted” — Passed→ PRS for Impact Analysis review
- Jul 20 '16
-
Aug 11 '16
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC priority 2016 · rank 1730“To endorse and forward to TAC the 7/14/16 PRS Report and Impact Analysis for NPRR782 with a recommended priority of 2016 and rank of 1730” — Passed→ TAC for consideration
-
Aug 25 '16
TAC TAC MeetingTACRecommended for Approval Recommended for approval“To recommend approval of NPRR782 as recommended by PRS in the 8/11/16 PRS Report” — Passed→ Board for consideration
-
Oct 11 '16
BOARD Board of Directors MeetingBOARDApproved Recommended for approval“To approve NPRR782 as recommended by TAC in the 8/25/16 TAC Report” — Passed