NPRR #767 · Revision Request
NPRR767 Commitment by RUC for Long Lead Time Resource
ReasonMarket efficiencies or enhancements
Created2016-05-12
Approved2016-10-11
Sections Affected
5.6.2
Summary
This Nodal Protocol Revision Request (NPRR) changes the eligibility check for the startup portion of the Reliability Unit Commitment (RUC) Make-Whole Payment. Resources with lead times longer than six hours may submit a Settlement dispute to have their Resource-specific startup times considered when determining eligibility for Startup Costs to be included in the RUC Make-Whole Payment calculation.
Timeline
- Apr 21 '16
-
May 4 '16
Listed without action at 1 meeting
-
May 12 '16
PRS PRS MeetingPRSRecommended for Approval Recommended for approval“To recommend approval of NPRR767 as submitted.” — Passed→ Impact Analysis Consideration
- May 13 '16
-
May 18 '16
Listed without action at 1 meeting
-
Jun 16 '16
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC“To endorse and forward to TAC the 5/12/16 PRS Report and the Impact Analysis for NPRR767.” — Passed→ Revision Request Consideration
-
Jul 28 '16
TAC TAC MeetingTACRecommended for Approval Recommended for approval“To recommend approval of NPRR767 as recommended by PRS in the 6/16/16 PRS Report.” — Passed→ Revision Request Consideration
- Aug 9 '16
-
Oct 11 '16
BOARDEmail Vote / Unlisted MeetingBOARDApproved Approved“To approve NPRR767 as recommended by TAC in the 7/28/16 TAC Report with an ERCOT Board action effective date of 8/9/16.” — Passed
-
—
Posted since the last meeting