NPRR767  Commitment by RUC for Long Lead Time Resource

Approved sponsor ERCOT posted 2016-04-21 ercot.com
ReasonMarket efficiencies or enhancements
Created2016-05-12
Approved2016-10-11
Sections Affected
5.6.2
Summary
This Nodal Protocol Revision Request (NPRR) changes the eligibility check for the startup portion of the Reliability Unit Commitment (RUC) Make-Whole Payment. Resources with lead times longer than six hours may submit a Settlement dispute to have their Resource-specific startup times considered when determining eligibility for Startup Costs to be included in the RUC Make-Whole Payment calculation.