ERCOT·WATCH Search ercot.com  ⌕
NPRR #753 · Revision Request

NPRR753  Allow AMS Data Submittal Process for TDSP-Read Non-Modeled Generators

Approved sponsor ERCOT posted 2016-01-26 ercot.com
ReasonAddresses current operational issues. Market efficiencies/enhancements
Created2016-02-11
Approved2016-10-11
Sections Affected
1.3.1.1 and 10.9
Summary
This Nodal Protocol Revision Request (NPRR) allows the option of using the Advanced Metering System (AMS) data submittal process for all Transmission and/or Distribution Provider (TDSP)-read Non-Modeled Generators; and requires an Interval Data Recorder (IDR) Meter for Block Load Transfer (BLT) metering points registered for Settlements in accordance with Section 6.5.9.5.1, Registration and Posting of BLT Points.
Timeline