NPRR #729 · Revision Request
NPRR729 Clarification of Metering Requirements for Resources
ReasonAddresses current operational issues. Market efficiencies/enhancements.
Created2015-09-10
Approved2015-12-08
Sections Affected
10.9
Summary
This Nodal Protocol Revision Request (NPRR) clarifies the metering requirements for Resources, specifically Interval Data Recorder (IDR) Meters versus IDRs.
Timeline
- Aug 14 '15
-
Sep 10 '15
PRS PRS MeetingPRSRecommended for Approval Recommended for approval“To recommend approval of NPRR729 as submitted” — Passed→ PRS for Impact Analysis review
- Sep 16 '15
-
Oct 15 '15
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC“To endorse and forward to TAC the 9/10/15 PRS Report and Impact Analysis for NPRR729” — Passed→ TAC for consideration
-
Oct 29 '15
TAC TAC MeetingTACRecommended for Approval Recommended for approval“To recommend approval of NPRR729 as recommended by PRS in the 10/15/15 PRS Report” — Passed→ Board for consideration
-
Dec 8 '15
BOARD Board of Directors MeetingBOARDApproved Recommended for approval“To approve NPRR729 as recommended by TAC in the 10/29/15 TAC Report” — Passed
-
—
Posted since the last meeting