NPRR #674 · Revision Request
NPRR674 Clarification of Water Supply Rights Documentation
ReasonAddresses current operational issues.
Created2015-01-15
Approved2015-06-09
Sections Affected
3.2.6.2.2
Summary
This Nodal Protocol Revision Request (NPRR) clarifies that an Interconnecting Entity (IE) meets the water supply condition for including a non-wind Generation Resource in the total capacity estimate when it demonstrates that it has obtained rights to water supplies by way of a contract or permit. The Protocols’ current use of the term "water rights" might be interpreted to suggest that only government-issued water permits meet this condition, when both contractual and permit-based rights should be understood to suffice.
Timeline
- Dec 2 '14
-
Jan 15 '15
PRS PRS MeetingPRSDeferred/Tabled Tabled Referred → WMS“To table NPRR674 and refer the issue to WMS.” — Passed→ Language Consideration
- Feb 4 '15
-
Feb 12 '15
Listed without action at 1 meeting
-
Mar 12 '15
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Amended by the Mar 5 '15 ERCOT comments“To recommend approval of NPRR674 as amended by the 3/5/15 ERCOT comments and revised by PRS” — Passed→ Impact Analysis Consideration
-
Apr 16 '15
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC“To endorse and forward to TAC the 3/12/15 PRS Report and the Impact Analysis for NPRR674.” — Passed→ Revision Request Consideration
-
May 28 '15
TAC TAC MeetingTACRecommended for Approval Recommended for approval“To recommend approval of NPRR674 as recommended by PRS in the 4/16/15 PRS Report.” — Passed→ Revision Request Consideration
-
Jun 9 '15
BOARD Board of Directors MeetingBOARDApproved Approved“To approve NPRR674 as recommended by TAC in the 5/28/15 TAC Report.” — Passed
-
—