NPRR #665 · Revision Request
NPRR665 As-Built Clarification of Reliability Deployment Price Adder
ReasonAdministrative and creates Market efficiencies and enhancements
Created2014-11-06
Approved2015-02-10
Sections Affected
6.3.26.5.7.36.5.7.3.1
Summary
Details how the Energy Offer Curves for Reliability Unit Commitment (RUC)-Committed Resources will be extended or created for the Security-Constrained Economic Dispatch (SCED) and the pricing run to determine the Reliability Deployment Price Adder; and clarifies language for related data that will be sent and/or posted during the Operating Hour.
Timeline
- Oct 22 '14
-
Nov 6 '14
PRS PRS MeetingPRSRecommended for Approval Recommended for approval“To recommend approval of NPRR665 as revised by PRS.” — Passed→ PRS for IA review.
- Nov 12 '14
-
Dec 11 '14
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC“To endorse and forward to TAC the 11/6/14 PRS Report and the Impact Analysis for NPRR665.” — Passed→ TAC for consideration.
-
Dec 18 '14
TAC TAC MeetingTACRecommended for Approval Recommended for approval“To recommend approval of NPRR665 as recommended by PRS in the 12/11/14 PRS Report.” — Passed→ ERCOT Board for consideration.
- Feb 9 '15
-
Feb 10 '15
BOARDEmail Vote / Unlisted MeetingBOARDApproved Approved“To approve NPRR665 as recommended by TAC in the 12/18/14 TAC Report.” — Passed
-
—