NPRR #635 · Revision Request

NPRR635  Clarification of Congestion Revenue Right Source/Sink Points

Approved sponsor Boston Energy posted 2014-06-25 ercot.com
ReasonAddresses current operational issues and enhances market efficiencies.
Created2014-07-17
Approved2014-10-14
Sections Affected
3.10.33.10.3.1
Summary
This Nodal Protocol Revision Request (NPRR) will establish that Resource Settlement Points are retained in ERCOT Congestion Revenue Right (CRR) and Day-Ahead Market (DAM) models until there is no further Resource association with the Settlement Point.
Timeline