NPRR618 Market Notices for Resettlement Statements and True-up Settlement Timeline Changes
ReasonAddresses current operational issues.
Created2014-05-15
Approved2014-08-12
Sections Affected
9.2.69.5.79.5.9
Summary
This Nodal Protocol Revision Request (NPRR) replaces requirements to post Notices on the Market Information System (MIS) for communication of Day-Ahead Market (DAM) and Real-Time Market (RTM) Resettlements and True-Up Settlement timeline changes with Market Notices.
Timeline
- Apr 29 '14
-
May 14 '14
Listed without action at 1 meeting
-
May 15 '14
PRS PRS MeetingPRSRecommended for Approval Recommended for approval“To recommend approval of NPRR618 as submitted.” — Passed→ PRS for Impact Analysis review.
- May 22 '14
-
Jun 11 '14
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC“To endorse and forward the 5/15/14 PRS Report and Impact Analysis for NPRR618 to TAC.” — Passed→ TAC for consideration.
-
Jun 26 '14
TAC TAC MeetingTACRecommended for Approval Recommended for approval“To recommend approval of NPRR618 as recommended by PRS in the 6/11/14 PRS Report.” — Passed→ ERCOT Board for consideration.
-
Aug 12 '14
BOARD Board of Directors MeetingBOARDApproved Approved“To approve NPRR618 as recommended by TAC in the 6/26/14 TAC Report.” — Passed
-
—