NPRR #615 · Revision Request
NPRR615 PVGR Forecasting
ReasonAddresses current operational issues; adds market efficiencies and enhancements; and incorporates Photovoltaic power forecasts into system operations
Created2014-05-15
Approved2014-08-12
Sections Affected
2.12.23.9.13.134.2.35.7.45.7.4.1.16.3.1
Summary
This NPRR establishes a definition for Short-Term PhotoVoltaic Power Forecast (STPPF) and clarifies the use of the resulting forecast within the Protocols. It is requested that WMS recommend a value for X in Section 4.2.3.
Timeline
- Apr 16 '14
-
May 15 '14
PRS PRS MeetingPRSDeferred/Tabled Tabled Referred → WMS“To table and refer the issue to WMS” — Passed→ PRS for consideration
- Jun 4 '14
-
Jun 11 '14
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Amended by the Jun 6 '14 WMS comments“To recommend approval as amended by the 6/6/14 WMS comments” — Passed→ PRS for Impact Analysis review
- Jun 18 '14
-
Jul 17 '14
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC“To endorse and forward to 6/11/14 PRS Report and Impact Analysis to TAC” — Passed→ TAC for consideration
-
Jul 31 '14
TAC TAC MeetingTACRecommended for Approval Recommended for approval“To recommend approval as recommended by PRS in the 7/17/14 PRS Report” — Passed→ ERCOT Board for consideration
-
Aug 12 '14
BOARD Board of Directors MeetingBOARDApproved Approved“To approve NPRR615 as recommended by TAC in the 07/31/14 TAC Report” — Passed