NPRR #579 · Revision Request
NPRR579 Amendment to the Minimum PTP Option Bid Price Approval Timeline
ReasonThis NPRR will provide additional flexibility to TAC and the ERCOT Board in the development of their meeting calendars.
Created2013-11-21
Approved2013-12-10
Sections Affected
7.7.1
Summary
This Nodal Protocol Revision Request (NPRR) amends the timing of the review of the Minimum Point-to-Point (PTP) Option Bid Price by TAC and the ERCOT Board. The current language specifically indicates that action should be taken each year during the month of January. The revision removes the reference to a specific month and states that the process should instead occur "at least annually." The language is also changed to only require annual review by TAC. The ERCOT Board would still review the Minimum PTP Option Bid Price when a change is being recommended by TAC through the NPRR process.
Timeline
- Nov 6 '13
-
Nov 21 '13
PRS Protocol Revision Subcommittee (PRS) MeetingPRSRecommended for Approval Recommended for approval“To recommend approval of NPRR579 as submitted.” — Passed→ TAC consideration of NPRR579
-
Dec 3 '13
TAC Technical Advisory Committee (TAC) MeetingTACRecommended for Approval Recommended for approval“To recommend approval of NPRR579 as recommended by PRS in the 11/21/13 PRS Report.” — Passed→ ERCOT Board consideration of NPRR579
-
Dec 10 '13
BOARD Board of Directors MeetingBOARDApproved Approved“To approve NPRR579 as recommended by TAC in the 12/3/13 TAC Report.” — Passed
-
—