NPRR578 Restores RUC Decommitment Charge Language Deleted in NPRR416
ReasonSection 5.7.6 was unintentionally deleted as part of NPRR416. The language in Section 5.7.6 provides the mechanism to uplift the charges to the Load Serving Entity (LSE) based on Load Ratio Share (LRS) when ERCOT must pay a Resource, as described in Section 5.7.3, Payment When ERCOT Decommits a QSE-Committed Resource.
Created2013-11-21
Approved2013-12-10
Sections Affected
5.5.25.7.6
Summary
This NPRR deletes the grey box in Section 5.7.6 that would remove the Reliability Unit Commitment (RUC) Decommitment Charge upon implementation of NPRR416; and clarifies Settlement treatment of RUC-Committed blocks that span an Operating Day and are opted out.
Timeline
- Nov 6 '13
-
Nov 21 '13
PRS Protocol Revision Subcommittee (PRS) MeetingPRSRecommended for Approval Recommended for approval“To recommend approval of NPRR578 as submitted.” — Passed→ TAC for consideration.
-
Dec 3 '13
TAC Technical Advisory Committee (TAC) MeetingTACRecommended for Approval Recommended for approval“To recommend approval of NPRR578 as recommended by PRS in the 11/21/13 PRS Report.” — Passed→ ERCOT Board for consideration.
-
Dec 10 '13
BOARD Board of Directors MeetingBOARDApproved Approved“To approve NPRR578 as recommended by TAC in the 12/3/13 TAC Report.” — Passed
-
—