NPRR #568 · Revision Request
NPRR568 Real-Time Reserve Price Adder Based on Operating Reserve Demand Curve
ReasonTo implement the concepts presented and address concerns raised at the January 24, 2013 PUCT workshop regarding Docket No. 40000.
Created2013-10-18
Approved2013-11-19
Sections Affected
2.12.23.5.2.13.5.2.23.5.2.33.5.2.43.5.2.63.96.36.3.26.4.3.16.4.3.2 (delete)6.4.3.3 (delete)6.5.5.26.5.7.36.5.9.26.6.16.6.1.16.6.1.26.6.3.16.6.106.7.4 (new)6.7.5 (new)8.1.18.1.1.28.1.1.2.18.1.1.2.1.6 (new)8.1.1.2.1.7 (new)8.1.1.4.4 (new)8.1.1.4.5 (new)9.5.3
Summary
This NPRR requires ERCOT to implement an Operating Reserve Demand Curve (ORDC) in the Real-Time Market (RTM) to determine the Real-Time price adder for Real Time Settlement Point Prices. The Real-Time price adder reflects the price for reserves available in the ERCOT System based on the loss of Load probability at that reserve level. The addition of this price adder to the Real Time Settlement Point Price ensures that the Real Time Settlement Point Price reflects the opportunity cost of reserve scarcity. A new Other Binding Document, "Methodology for Implementing Operating Reserve Demand Curve (ORDC) to Calculate Real-Time Reserve Price Adder," a draft of which is attached to this NPRR as Attachment 1, will describe the methodologies for developing the ORDC and determining the reserve price adder using the ORDC. It will also list the values of the parameters to be used. Additional details about the methodology and a backcast based on the methodology can be found in filings under Public Utility Commission of Texas (PUCT) Docket No. 40000, Commission Proceeding to Ensure Resource Adequacy in Texas, and Key Documents posted on the Resource Adequacy Task Force home page . Since Real-Time co-optimization of energy and Ancillary Services will not be implemented at this time, to ensure that Resources are indifferent between providing energy and reserves in Real-Time, an Ancillary Service imbalance Settlement will be performed. Reliability Unit Commitment (RUC) Resources and Reliability Must-Run (RMR) Units are removed from this Ancillary Service imbalance payment for their On-Line capacity in Real-Time since making the payment and clawing it back would result in the same financial outcome but with significant changes to the Protocols.
Timeline
- Sep 19 '13
-
Oct 4 '13
Listed without action at 1 meeting
- Oct 9 '13
-
Oct 17 '13
PRS Protocol Revision Subcommittee (PRS) Meeting
- 568NPRR-08 ERCOT Comments - Attachment 1 101113
- 568NPRR-09 EMMT Comments 101513
- 568NPRR-07 ERCOT Comments 101113
- 568NPRR-10 TPS Comments 101513
- 568NPRR-11 EMMT Comments 101613
- 568NPRR-12 EMMT Comments - Attachment 1 101613
- 568NPRR-13 TIEC and CPS Energy Comments 101613
- 568NPRR-14 Luminant Comments 101613
-
Oct 18 '13
PRSEmail Vote / Unlisted MeetingPRSRecommended for Approval Recommended for approval Amended by the Oct 8 '13 Morgan Stanley comments Amended by the Oct 11 '13 ERCOT comments Amended by the Oct 15 '13 EMMT comments Amended by the Oct 16 '13 Luminant comments priority 2013 · rank 70 Referred → WMS Referred → WMS“To recommend approval of NPRR568 as amended by the 10/8/13 Morgan Stanley comments, 10/11/13 ERCOT comments, 10/15/13 EMMT comments and 10/16/13 Luminant comments and as revised by PRS with a recommended priority of 2013, rank of 70 and category of Regulatory; to request that the Impact Analysis separate out the impacts associated with each of the following: (A) the 10/11/13 ERCOT comments (including the revision related to Wind-powered Generation Resources introduced in the 10/15/13 EMMT comments), (B) the 10/8/13 Morgan Stanley comments, and (C) the 10/18/13 PRS revisions; to refer the issue of Load Resources providing OFF10 or OFF30 capacity to WMS for assignment to the Demand Side Working Group (DSWG); and to refer review of the verification of Real-Time Production Potential to WMS for assignment to the Qualified Scheduling Entity (QSE) Managers Working Group (QMWG).” — Passed→ TAC consideration of NPRR568
- Oct 30 '13
-
Nov 7 '13
TAC Technical Advisory Committee (TAC) MeetingTACRecommended for Approval Recommended for approval Amended by the Nov 6 '13 ERCOT comments“To recommend approval of the "Methodology for Implementing Operating Reserve Demand Curve (ORDC) to Calculate Real-Time Reserve Price Adder" as amended by the 11/6/13 ERCOT comments (Attachment 1) and as revised by TAC with a proposed effective date of upon implementation of NPRR568 and to add the methodology to the Other Binding Document List.” — Passed→ ERCOT Board consideration of NPRR568
-
Nov 19 '13
BOARD Board of Directors MeetingBOARDApproved Approved“To approve NPRR568 as recommended by TAC in the 11/7/13 TAC Report.” — Passed
-
Dec 3 '13
Listed without action at 22 meetings (Dec 3 '13 – Apr 6 '15)
- Technical Advisory Committee (TAC) Meeting
- WMS Meeting
- PRS Meeting
- TAC Meeting
- Board of Directors Meeting
- COPS Meeting
- TAC Meeting
- WMS Meeting
- TAC Meeting
- WMS Meeting
- TAC Meeting
- QMWG Meeting
- WMS Meeting
- QMWG Meeting
- TAC Meeting
- WMS Meeting
- TAC Meeting
- QMWG Meeting
- WMS Meeting
- QMWG Meeting
- QMWG Meeting
- WMS Meeting