NPRR564  Thirty-Minute Emergency Response Service (ERS) and Other ERS Revisions

Approved Urgent sponsor ERCOT posted 2013-08-21 ercot.com
ReasonERCOT is proposing an ERS product with a thirty-minute ramp rate (ERS-30) in order to secure additional Demand Response capability and further strengthen reliability in the ERCOT Region. Since July 15, 2012, ERCOT has been conducting a pilot project to assess the operational benefits of an ERS-30 product. Based on the results of the pilot observed to date, ERCOT has concluded that such a product would bring additional participation from Loads that cannot meet a ten-minute ramp requirement, thereby providing additional reliability benefits. While a longer ramp means the product is less responsive than the existing ten-minute ERS product (ERS-10), being able to deploy it earlier during an Energy Emergency Alert gives ERCOT an additional reliability tool that should be especially valuable during foreseeable peak conditions, such as summer afternoons. This NPRR also proposes to introduce a clearing price (with some differences from NPRR537, ERS Clearing Price) in lieu of as-bid pricing, which should discourage inefficient price-chasing. Additionally, proposed changes to the maximum deployment duration language (similar to that proposed in NPRR536, ERS Time Obligation Certainty) should ensure that this deployment cap is applied to individual ERS Resources so as to maximize the operational benefit of the service. This NPRR also proposes that individual Resources will be subject to payment reductions that vary exponentially with the degree of individual performance failure in the event of a QSE-level failure, instead of being automatically suspended.
Created2013-09-19
Approved2013-11-19
Sections Affected
2.13.14.33.14.3.13.14.3.23.14.3.33.14.3.46.5.9.4.26.6.11.16.6.11.28.1.3.1.18.1.3.1.28.1.3.1.38.1.3.1.3.18.1.3.1.3.28.1.3.1.3.38.1.3.1.48.1.3.28.1.3.38.1.3.3.18.1.3.48.49.14.5
Summary
This Nodal Protocol Revision Request (NPRR) proposes a 30-minute Emergency Response Service (ERS) product and recommends other changes to ERS more generally, including the following: 1. Introduces Settlement based on a clearing price instead of individual Qualified Scheduling Entity (QSE) offer price. 2. Introduces stronger financial penalties for non-performance in a single ERS Standard Contract Term but removes mandatory suspensions. 3. Clarifies obligations of ERS Resources when deployments cross over multiple ERS Time Periods. 4. Authorizes ERCOT to provide times and dates of particular Resource deployments to QSEs in order to allow them to analyze past performance of newly acquired ERS sites. 5. Prohibits participation by sites associated with Dynamically Scheduled Resources (DSRs). 6. Clarifies that ERS Generators and ERS Loads are to be evaluated together when an ERS Generator is providing backup to an ERS Load.
Timeline