NPRR #535 · Revision Request

NPRR535  Resource Status Startup - Shutdown

Withdrawn sponsor GDF Suez Energy Marketing NA posted 2013-04-11 next action Language Consideration ercot.com
ReasonIn the current market design a Resource with ICCP status of SHUTDOWN may incur Base Point Deviation Charges.
Created2013-05-16
Sections Affected
6.5.7.8
Summary
This Nodal Protocol Revision Request (NPRR) would allow Inter-Control Center Communications Protocol (ICCP) data required by ERCOT to include a Resource Status for ONTEST, STARTUP, and SHUTDOWN. A Resource using ONTEST or STARTUP status is not available to Security-Constrained Economic Dispatch (SCED) calculations. We believe that A Resource using SHUTDOWN status should also not be available to SCED calculations.
Timeline