NPRR #462 · Revision Request
NPRR462 Removal of Consumer Benefit Test from the ERCOT Planning Criteria
ReasonPUCT Project 39537 removed the consumer benefit test from P.U.C. Subst. R. 25.101, Certification Criteria, and therefore should be removed from the ERCOT planning criteria for consistency.
Created2012-05-17
Approved2012-07-17
Sections Affected
3.11.2
Summary
This Nodal Protocol Revision Request (NPRR) removes the consumer benefit test from the ERCOT planning criteria consistent with the Public Utility Commission of Texas (PUCT) Project 39537, Rulemaking to Implement HB 971, Relating to Economic Criteria for a Certificate of Convenience and Necessity for an Electric Transmission Project.
Timeline
- May 2 '12
-
May 17 '12
PRS Protocol Revision Subcommittee (PRS) MeetingPRSRecommended for Approval Recommended for approval Amended by the May 16 '12 Oncor comments“To recommend approval of NPRR462 as amended by the 5/16/12 Oncor comments and as revised by PRS” — Passed→ PRS IA Review
- May 30 '12
-
Jun 21 '12
PRS Protocol Revision Subcommittee (PRS) MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC“To endorse and forward the 5/17/12 PRS Report and Impact Analysis for NPRR462 to TAC.” — Passed→ TAC for consideration.
-
Jun 28 '12
TAC Technical Advisory Committee (TAC) MeetingTACRecommended for Approval Recommended for approval“To recommend approval of NPRR462 as recommended by PRS in the 6/21/12 PRS Report” — Passed→ ERCOT Board Consideration
-
Jul 17 '12
BOARD Board of Directors MeetingBOARDApproved Approved“To approve NPRR462 as recommended by TAC in the 6/28/12 TAC Report.” — Passed