NPRR442  Energy Offer Curve Requirement for Generation Resources Providing Reliability Must-Run Service

Approved Urgent sponsor Morgan Stanley posted 2012-02-03 ercot.com
ReasonTo address concerns raised at the October 27, 2011 Public Utility Commission of Texas (PUCT) Open Meeting regarding Project No. 37897, PUC Proceeding Relating to Resource and Reserve Adequacy and Shortage Pricing.
Created2012-02-23
Approved2012-05-15
Sections Affected
4.4.84.4.9.4.16.4.3
Summary
This Nodal Protocol Revision Request (NPRR) adds the following requirements for Reliability Must-Run (RMR) Units that ERCOT has made available for commitment in accordance with Section 4.4.8: (1) A requirement for the RMR Unit’s Energy Offer Curve to be set at the System-Wide Offer Cap (SWCAP) for Generation Resources providing RMR Service; and (2) A requirement for ERCOT to construct a Mitigated Offer Cap curve for Resources contracted for capacity pursuant to paragraph (2) of Section 6.5.1.1, ERCOT Control Area Authority, such that those Resources are not mitigated in Security-Constrained Economic Dispatch (SCED) and hence will be Dispatched for local constraints only if the prices are higher than or equal to SWCAP. If a Reliability Unit Commitment (RUC) unit is deployed, ERCOT will submit an Output Schedule or Energy Offer Curve for the Generation Resource at the SWCAP.
Timeline