NPRR #440 · Revision Request
NPRR440 Consideration of Generation Availability in RMR Analyses
ReasonThe revisions proposed by this NPRR are necessary to ensure that sufficient Generation Resources are available in transmission-constrained areas to reliably manage constraints over at least a five year planning horizon.
Created2012-02-23
Rejected2012-03-22
Sections Affected
3.14.13.14.1.2
Summary
The Nodal Protocol Revision Request (NPRR) modifies provisions that relate to Reliability Must-Run (RMR) analysis to ensure generation availability is assessed by ERCOT in RMR evaluations over at least a five year planning horizon.
Timeline
-
Jan 30 '12
PRSFiled by Paul Rocha on behalf of CenterPoint Energy
-
Feb 23 '12
PRS Protocol Revision Subcommittee (PRS) MeetingPRSDeferred/Tabled Tabled Referred → ROS“To table NPRR440 and refer the issue to ROS.” — Passed→ PRS for consideration.
- Mar 7 '12
-
Mar 8 '12
Listed without action at 1 meeting
-
Mar 22 '12
PRS Protocol Revision Subcommittee (PRS) MeetingPRSRejected Recommended for approval Amended by the Feb 16 '12 Luminant Energy Company comments“To to recommend approval of NPRR440 as amended by the 2/16/12 Luminant Energy Company comments” — Failed
- Apr 5 '12