NPRR440  Consideration of Generation Availability in RMR Analyses

Rejected sponsor Paul Rocha on behalf of CenterPoint Energy posted 2012-01-30 ercot.com
ReasonThe revisions proposed by this NPRR are necessary to ensure that sufficient Generation Resources are available in transmission-constrained areas to reliably manage constraints over at least a five year planning horizon.
Created2012-02-23
Rejected2012-03-22
Sections Affected
3.14.13.14.1.2
Summary
The Nodal Protocol Revision Request (NPRR) modifies provisions that relate to Reliability Must-Run (RMR) analysis to ensure generation availability is assessed by ERCOT in RMR evaluations over at least a five year planning horizon.