NPRR #425 · Revision Request
NPRR425 Creation of a WGR Group for GREDP and Base Point Deviation Evaluation and Mixing Turbine Types Within a WGR (formerly "Creation of a WGR Group for GREDP and Base Point Deviation Evaluation")
ReasonIn Protocol Revision Request (PRR) 830, Reactive Power Capability Requirement, ERCOT modified the definition of a "Wind-powered Generation Resource" in order to obtain a more accurate representation of the reactive capabilities of the aggregated turbines of the same model and size for reactive modeling purposes. However, for Dispatch purposes, many Qualified Scheduling Entities (QSEs) / Resource Entities representing WGRs are not able to independently Dispatch those WGRs due to control limitations. Therefore, ERCOT believes an acceptable solution to this problem is to create a WGR Group for Dispatch purposes while still maintaining the WGR definition for reactive modeling purposes. The creation of the WGR Group also addresses the Base Point Deviation treatment for these WGRs under their current operational capabilities. By allowing multiple wind turbine models or sizes to be combined in a single WGR, Market Participants may avoid the burden of having to register and operate additional WGRs due to the replacement of wind turbines if the replacement turbines have similar, if not exact characteristics, or due to the installation of a de minimis number of turbines that may have different characteristics from the majority of turbines in the WGR for the purpose of testing new technologies, so long as it does not reduce ERCOT’s ability to model pre- and post-contingency conditions on the ERCOT Transmission Grid.
Created2011-11-17
Approved2012-11-13
Sections Affected
2.13.10.7.26.6.5.28.1.1.4.1
Summary
This Nodal Protocol Revision Request (NPRR) provides that Wind-powered Generation Resources (WGRs) meeting registration requirements will be evaluated for Generation Resource Energy Deployment Performance (GREDP) and Base Point Deviation as groups of WGRs rather than individual WGRs. This NPRR also permits multiple wind turbine models or sizes to be combined in a single WGR if certain criteria are met.
Timeline
-
Nov 1 '11
PRSFiled by ERCOT
- Nov 17 '11
-
Dec 2 '11
Listed without action at 2 meetings (Dec 2 '11 – Dec 7 '11)
- Dec 15 '11
-
Jan 6 '12
Listed without action at 4 meetings (Jan 6 '12 – Feb 8 '12)
- Feb 15 '12
-
Feb 23 '12
PRS Protocol Revision Subcommittee (PRS) MeetingPRSRecommended for Approval Recommended for approval Amended by the Feb 17 '12 E.ON comments“To recommend approval of NPRR425 as amended by the 2/17/12 E.ON comments.” — Passed→ PRS Impact Analysis review
- Feb 29 '12
-
Mar 22 '12
PRS Protocol Revision Subcommittee (PRS) MeetingPRSDeferred/Tabled Tabled Referred → WMS Referred → QMWG“To table NPRR425 and to request that WMS and the QSE Managers Working Group (QMWG) review NPRR425.” — Passed→ PRS Impact Analysis review
- Mar 30 '12
- Apr 11 '12
-
Apr 12 '12
Listed without action at 1 meeting
-
Apr 19 '12
PRS Protocol Revision Subcommittee (PRS) MeetingPRSDeferred/Tabled Tabled“To table NPRR425.” — Passed→ PRS Impact Analysis review
- Apr 30 '12
-
May 4 '12
Listed without action at 4 meetings (May 4 '12 – May 17 '12)
- Jun 12 '12
-
Jun 14 '12
Listed without action at 1 meeting
-
Jun 21 '12
PRS Protocol Revision Subcommittee (PRS) MeetingPRSRecommended for Approval Recommended for approval Amended by the Jun 11 '12 ERCOT comments Remanded → PRS“To endorse the 2/23/12 PRS Report as amended by the 6/11/12 ERCOT comments and to direct that NPRR425 and a revised Impact Analysis return to the July 2012 PRS meeting.” — Passed→ PRS Impact Analysis review
- Jun 27 '12
-
Jul 19 '12
PRS Protocol Revision Subcommittee (PRS) MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC priority 2013 · rank 770“To endorse and forward the 6/21/12 PRS Report and Impact Analysis for NPRR425 to TAC with a recommended priority of 2013 and rank of 770.” — Passed→ TAC consideration of NPRR425
-
Sep 7 '12
TAC Technical Advisory Committee (TAC) MeetingTACDeferred/Tabled Tabled“To table NPRR425.” — Passed→ TAC consideration of NPRR425
-
Oct 4 '12
TAC Technical Advisory Committee (TAC) MeetingTACRecommended for Approval Recommended for approval Amended by the Sep 26 '12 ERCOT comments Amended by the Sep 27 '12 Wind Coalition comments“To recommend approval of NPRR425 as recommended by PRS in the 7/19/12 PRS Report and as amended by the 9/26/12 ERCOT comments and 9/27/12 Wind Coalition comments.”→ ERCOT Board consideration
-
Nov 13 '12
BOARD Board of Directors MeetingBOARDApproved Recommended for approval“To approve NPRR425 as recommended by TAC in the 10/4/12 TAC Report.” — Passed
-
Jul 30 '13
Listed without action at 2 meetings (Jul 30 '13 – Sep 12 '13)