NPRR #423 · Revision Request
NPRR423 Add Voltage Support Requirement for IRRs and Allow SCADA Control of Static VAr Devices if Approved by ERCOT (formerly "Add Voltage Support Requirement for IRRs and Allow Manual Control of Static VAr Devices if Approved by ERCOT")
ReasonSimilar to WGRs, solar power plants cannot have or have very limited reactive capability at output less than 10%. This NPRR will clarify the Reactive Power requirement for solar power plants. Paragraph (8) of Section 3.15 allows Generation Entities to submit ERCOT-specific proposals to meet the Reactive Power requirements. Depending on the location and size of those proposed static VAr devices, the Transmission Service Provider (TSP) may suggest that those devices are in the manual control mode to avoid undesired ERCOT System impacts, such as voltage swing during the switching of those VAr devices. This NPRR provides a solution for those proposed VAr devices operating in the manual control mode based on the agreement between the Generation Resource and TSP
Created2011-11-17
Approved2012-02-21
Sections Affected
3.15
Summary
This Nodal Protocol Revision Request (NPRR) includes Intermittent Renewable Resources (IRRs) in the voltage requirement and clarifies the reactive requirement to be the same as Wind-powered Generation Resources (WGRs). This NPRR also proposes that switchable static Volt-Ampere reactive (VAr) devices can be Supervisory Control and Data Acquisition (SCADA) controlled if approved by ERCOT.
Timeline
- Nov 2 '11
-
Nov 17 '11
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Amended by the Nov 14 '11 Oncor Electric Delivery comments“To recommend approval of NPRR423 as amended by the 11/14/11 Oncor Electric Delivery comments and as revised by PRS” — Passed→ PRS review the Impact Analysis
-
Dec 15 '11
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC“To endorse and forward the 11/17/11 PRS Report and Impact Analysis for NPRR423 to TAC” — Passed→ TAC consideration
-
Jan 5 '12
TAC Technical Advisory Committee (TAC) MeetingTACRecommended for Approval Recommended for approval“To recommend approval of NPRR423 as recommended by PRS in the 12/15/11 PRS Report.” — Passed→ Board consideration
-
Feb 21 '12
BOARD Board of Directors MeetingBOARDApproved Recommended for approval“To approve NPRR423 as recommended by TAC in the 1/5/12 TAC Report.” — Passed