ERCOT·WATCH Search ercot.com  ⌕
NPRR #418 · Revision Request

NPRR418  Reporting of Resource Forced Outages

Rejected sponsor ERCOT posted 2011-10-05 ercot.com
ReasonThis NPRR is needed increase operational awareness of ERCOT and provide more accurate and timely responses to Requests for Information (RFIs) to the Public Utility Commission of Texas (PUCT), Texas Reliability Entity (Texas RE) and other regulatory agencies on outaged Resource capacity. The existing Protocols allow a two-hour exemption for Forced Outages on Resources and Transmission Facilities, but during the February 2011 weather event, ERCOT was required to send RFIs to accurately confirm Resource Forced Outages that occurred, as they were not recorded in the ERCOT Outage Scheduler. The lack of timely Resource Forced Outage information hindered operation of the ERCOT System. In addition, the RFI process delayed reporting and created additional work for both ERCOT and Market Participants.
Created2011-10-20
Rejected2011-12-01
Sections Affected
3.1.4.53.1.4.6
Summary
This Nodal Protocol Revision Request (NPRR) will require all Resource Forced Outages to be entered into the Outage Scheduler.
Timeline