NPRR #332 · Revision Request

NPRR332  Revise QSGR Processes for COP Reporting of QSGR Assigned Off-Line Non-Spin and Application of Emergency Operations Settlement

Approved sponsor ERCOT posted 2011-02-25 ercot.com
ReasonThe process changes included in this NPRR: Clarify the QSE’s responsibilities in regard to its QSGR Resources that are providing Off-Line Non-Spin; and Reduce the communications demands placed on the QSE and ERCOT Operators to accommodate the application of the emergency operations Settlement provisions.
Created2011-03-24
Approved2011-07-19
Sections Affected
3.8.33.9.16.4.66.6.9
Summary
This Nodal Protocol Revision Request (NPRR): Clarifies the COP reporting requirements for a Quick Start Generation Resource (QSGR) that is providing Off-Line Non-Spinning Reserve (Non--Spin) Service in an amount that is greater than High Sustained Limit (HSL) minus Low Sustained Limit (LSL); and Removes the requirement for a Qualified Scheduling Entity (QSE) to contact the ERCOT Operator to request a "manual override" when a QSGR it represents is first deployed by Security-Constrained Economic Dispatch (SCED) from a zero Base Point to a Base Point that is less than the QSGR’s physical LSL. Emergency operations Settlement provisions for QSGR deployments by SCED will be managed internally by ERCOT.
Timeline