NPRR #324 · Revision Request

NPRR324  Conductor/Transformer Transmission Facility Rating

Approved sponsor ERCOT posted 2011-02-10 ercot.com
ReasonThe requirement for Conductor/Transformer Rating is required for compliance with North American Electric Reliability Corporation (NERC) Reliability Standard FAC-010, System Operating Limits Methodology for the Planning Horizon.
Created2011-03-24
Approved2011-07-19
Sections Affected
2.12.23.10.7.1.1
Summary
This Nodal Protocol Revision Request (NPRR) adds the Conductor/Transformer Rating, normally used for Rate C in the Annual Planning Model, as a fourth Transmission Facility Rating and adds the description from the Operating Guides to the Rating terms definitions in the Nodal Protocols.
Timeline