NPRR #317 · Revision Request
NPRR317 Clarification of Entity Responsible for Hydro Responsive Testing
ReasonThe current Protocol language requires ERCOT to post performance of hydro responsive testing for Qualified Scheduling Entities (QSE). This NPRR clarifies that hydro responsive testing is performed by the Generation Resource not the QSE.
Created2011-03-24
Approved2011-06-21
Sections Affected
8.1
Summary
This Nodal Protocol Revision Request (NPRR) clarifies the Entity responsible for hydro responsive testing.
Timeline
- Feb 4 '11
-
Mar 24 '11
PRS PRS MeetingPRSRecommended for Approval Recommended for approval“To recommend approval of NPRR317 as submitted.” — Passed→ PRS for Impact Analysis review.
-
Apr 21 '11
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC“To to endorse and forward the 3/24/11 PRS Report and Impact Analysis for NPRR317 to TAC.” — Passed→ TAC for consideration.
-
May 5 '11
TAC TAC MeetingTACRecommended for Approval Recommended for approval“To recommend approval of NPRR317 as recommended by PRS in the 4/21/11 PRS Report.” — Passed→ ERCOT Board for consideration.
-
Jun 21 '11
BOARD Board of Directors MeetingBOARDApproved Approved“To approve NPRR317 as recommended by TAC in the 5/5/11 TAC Report.” — Passed
-
—
Posted since the last meeting