NPRR #309 · Revision Request
NPRR309 Providing STWPF to QSEs Contractually Affiliated with WGR
ReasonBy receiving the WGR forecast directly from ERCOT, a QSE that purchases power from a WGR will be able to process the data in a timelier manner.
Created2011-02-17
Rejected2011-06-23
Sections Affected
4.2.2
Summary
The Nodal Protocols currently enable a Wind-powered Generation Resource (WGR) and the Qualified Scheduling Entity (QSE) representing that WGR to receive ERCOT’s Short-Term Wind Power Forecast (STWPF) for that WGR via the Messaging System and the Market Information System (MIS) Certified Area. This Nodal Protocol Revision Request (NPRR) would require ERCOT to provide the WGR forecast to any QSE contractually affiliated with that WGR.
Timeline
-
Jan 14 '11
PRSFiled by Lower Colorado River Authority (LCRA)
-
Feb 17 '11
PRS PRS MeetingPRSReferred Referred → WMS“To refer NPRR309 to WMS.” — Passed→ WMS consideration of NPRR309
- Mar 9 '11
-
Mar 24 '11
Listed without action at 4 meetings (Mar 24 '11 – May 11 '11)
-
May 19 '11
PRS PRS MeetingPRSRecommended for Approval Recommended for approval“To recommend approval of NPRR309 as submitted.” — Passed→ PRS Impact Analysis review
- Jun 23 '11
- Jul 7 '11