NPRR #306 · Revision Request
NPRR306 Revisions to Protected Information to Include Black Start Documents Considered CEII
ReasonThe Operations Working Group (OWG) proposes changes to the Protocols that, upon approval by the ERCOT Board, would require that Black Start Task Force (BSTF) meetings be closed to the public in order to ensure that the documents and discussions pertaining to Black Start Service are kept confidential and protected under CEII guidelines. This Protocol change would require all participants of the BSTF to sign a non-disclosure agreement.
Created2011-02-17
Approved2011-05-17
Sections Affected
1.3.6
Summary
This Nodal Protocol Revision Request (NPRR) revises Section 1.3.6 to include Black Start documents that meet the definition of Critical Energy Infrastructure Information (CEII).
Timeline
-
Jan 11 '11
PRSFiled by OWG
-
Feb 17 '11
PRS PRS MeetingPRSRecommended for Approval Recommended for approval“To recommend approval of NPRR306 as submitted” — Passed→ PRS IA Review
- Feb 23 '11
-
Mar 7 '11
Listed without action at 1 meeting
- Mar 10 '11
-
Mar 24 '11
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC“To endorse and forward the 2/17/11 PRS Report and Impact Analysis for NPRR306 to TAC” — Passed→ TAC Consideration
-
Apr 7 '11
TAC TAC MeetingTACRecommended for Approval Recommended for approval“To recommend approval of NPRR306 as recommended by PRS in the 3/24/11 PRS Report” — Passed→ ERCOT Board Consideration
-
Apr 7 '11
Listed without action at 1 meeting
- May 11 '11
-
May 17 '11
BOARD Board of Directors MeetingBOARDApproved Approved“To approve NPRR306 as recommended by TAC in the 4/7/11 TAC Report.” — Passed
-
—