NPRR #251 · Revision Request
NPRR251 Synchronization of PRR845, Definition for IDR Meters and Optional Removal of IDR Meters at a Premise Where an Advanced Meter Can be Provisioned
ReasonTo synchronize the Nodal Protocols with PRR845. This NPRR provides guidelines for the mandatory installation and removal of an IDR Meter as it relates to the use of provisioned Advanced Meters.
Created2010-07-22
Approved2010-09-21
Sections Affected
2.13.14.38.1.3.19.5.69.5.89.5.99.1810.2.210.3.2.310.3.3.310.910.9.110.9.210.9.311.4.3.118.618.6.118.6.218.6.318.6.518.6.6
Summary
This Nodal Protocol Revision Request (NPRR) synchronizes the Nodal Protocols with Protocol Revision Request (PRR) 845, Definition for IDR Meters and Optional Removal of IDR Meters at a Premise Where an Advanced Meter Can be Provisioned, which clarifies the meaning of an Interval Data Recorder (IDR) Meter and provides for optional removal of IDR Meters under certain conditions for Premises where an Advanced Meter can be provisioned by the Transmission and/or Distribution Service Provider (TDSP). This NPRR also inserts grey boxed language for reporting requirements in Sections 18.6.1 and 18.6.2, to be implemented post Texas Nodal Market Implementation Date, that were removed from PRR845 due to the impact on Nodal systems and therefore deemed "Not Needed for Go-Live" by the CEO Revision Request Review process.
Timeline
-
Jul 7 '10
PRSFiled by Terry Bates on behalf of the Retail Metering Working Group
- Jul 14 '10
-
Jul 22 '10
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Priority“To recommend approval of NPRR251 as submitted with a recommended priority of High for the proposed grey-box language.” — Passed→ PRS for Impact Analysis Review.
-
Aug 19 '10
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC Priority“To endorse and forward the 7/22/10 PRS Report with a recommended priority of High for the proposed grey-box language and Impact Analysis for NPRR251 to TAC.” — Passed→ TAC for consideration.
-
Sep 2 '10
TAC TAC MeetingTACRecommended for Approval Recommended for approval Priority“To recommend approval of NPRR251 as recommended by PRS in the 8/19/10 PRS Report with a recommended priority of High for the proposed grey-box language.” — Passed→ ERCOT Board for consideration.
-
Sep 21 '10
BOARDEmail Vote / Unlisted MeetingBOARDApproved Approved“To approved NPRR251 as recommended by TAC in the 9/2/10 TAC Report.” — Passed
- Feb 17 '11
- Mar 3 '11
- Sep 21 '11