NPRR #232 · Revision Request
NPRR232 Clarification of Block Load Transfer Registration and Deployment
ReasonBLTs occur generally in connection with Planned or Forced transmission or distribution Outages. Transfers are performed to facilitate Planned Outages for construction and maintenance and for localized Forced Outage recovery. This NPRR clarifies the registration process in light of these instances.
Created2010-05-20
Approved2010-09-21
Sections Affected
2.16.5.9.56.5.9.5.16.5.9.5.2
Summary
This Nodal Protocol Revision Request (NPRR) adds language to clarify the purpose of registering Block Load Transfers (BLTs) and to specify the instances of Load transfer between Control Areas for which registration is required or when optional. The proposed revision clarifies the role of Market Participants regarding registering a BLT and related roles.
Timeline
-
May 9 '10
PRSFiled by ERCOT
-
May 20 '10
PRS PRS MeetingPRSDeferred/Tabled Tabled“To table NPRR232 for one month.” — Passed→ PRS language consideration
-
Jun 17 '10
PRS PRS MeetingPRSDeferred/Tabled Tabled“To table NPRR232 for one month.” — Passed→ PRS language consideration
-
Jul 22 '10
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Amended by the Jul 15 '10 ERCOT comments“To recommend approval of NPRR232 as amended by the 7/15/10 ERCOT comments and as revised by PRS.” — Passed→ PRS Impact Analysis review
-
Aug 19 '10
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC“To endorse and forward the 7/22/10 PRS Report and Impact Analysis for NPRR232 to TAC.” — Passed→ TAC consideration of NPRR232
-
Sep 2 '10
TAC TAC MeetingTACRecommended for Approval Recommended for approval“To recommend approval of NPRR232 as recommended by PRS in the 8/19/10 PRS Report.” — Passed→ ERCOT Board consideration of NPRR232
-
Sep 21 '10
BOARDEmail Vote / Unlisted MeetingBOARDApproved Recommended for approval“To approve NPRR232 as recommended by TAC in the 9/2/10 TAC Report.” — Passed