NPRR #231 · Revision Request
NPRR231 Treatment of RMR Units in the Day-Ahead Market (formerly "Remove RMR Units from the Day-Ahead Market")
ReasonGeneration Resources providing RMR Service are typically needed only for maintaining local reliability until additional transmission or generation is constructed to eliminate the need for such service. Since their prices are fixed by contract and thus, not competitively priced, ERCOT should not be allowed to utilize such Resources in the ERCOT competitive market. Furthermore, RMR contracts are structured to capture fixed costs and energy costs associated with the Resource, not start or minimum generation costs, which are key parts of any Three-Part Supply Offer curve submitted by a competitive Resource.
Created2010-05-20
Approved2010-09-21
Sections Affected
4.14.2.1.14.4.84.6.2.14.6.2.3.2
Summary
This Nodal Protocol Revision Request (NPRR) removes ERCOT’s ability to submit Three-Part Supply Offer curves for any Generation Resource providing Reliability Must-Run (RMR) Service from participation in the Day-Ahead Market (DAM) and the Day-Ahead Reliability Unit Commitment (DRUC) process. However, ERCOT will still have the ability to use an RMR Resource to resolve local congestion issues through Verbal Dispatch Instruction (VDI). This NPRR also proposes non-substantive administrative changes, such as correcting acronym and defined term usage. These are shown below with the author "ERCOT Market Rules."
Timeline
-
May 6 '10
PRSFiled by Luminant
- May 20 '10
- Jun 8 '10
- Jun 16 '10
-
Jun 17 '10
PRS PRS MeetingPRSReferred Referred → NATF“To refer NPRR231 to the Nodal Advisory Task Force (NATF)” — Passed→ NATF Review
- Jun 23 '10
- Jul 8 '10
- Jul 21 '10
-
Jul 22 '10
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Amended by the Jul 21 '10 WMS comments Action“To recommend approval of NPRR231 as amended by the 7/21/10 WMS comments and as revised by PRS and requested that ERCOT Staff report back on how they will manage RMR units in the DAM” — Passed→ PRS IA Review
-
Aug 19 '10
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC“To endorse and forward the 7/22/10 PRS Report and Impact Analysis to TAC via a roll call vote” — Passed→ TAC Consideration
-
Sep 2 '10
TAC TAC MeetingTACRecommended for Approval Recommended for approval Amended by the TAC comments“To recommend approval of NPRR238 as recommended by PRS in the 8/19/10 PRS Report and as revised by TAC” — Passed→ Board Consideration
-
Sep 21 '10
BOARDEmail Vote / Unlisted MeetingBOARDApproved Recommended for approval“To approve NPRR231 as recommended by TAC in the 9/2/10 TAC Report” — Passed
-
—
Posted since the last meeting