NPRR189  Ancillary Service Deployment Clarification

Approved sponsor ERCOT posted 2009-07-24 next action Consideration ercot.com
ReasonThis NPRR is needed to provide more clarity and make the Nodal Protocols consistent with Energy Management System (EMS)/Market Management System (MMS) whitepaper and current MMS implementation.
Created2009-08-25
Approved2009-10-20
Sections Affected
6.4.8.16.4.8.26.5.5.26.5.7.26.5.7.6.2.16.5.7.6.2.26.5.7.6.2.3
Summary
This Nodal Protocol Revision Request (NPRR) clarifies the difference between Ancillary Service capacity deployment and energy deployment and how it affects Security-Constrained Economic Dispatch (SCED). This NPRR also proposes non-substantive administrative changes, such as correcting acronym and defined term usage and section references.
Timeline