NPRR #157 · Revision Request
NPRR157 Extending Black Start Service Bid Timeline
ReasonThis NPRR will give transmission operators and Market Participants more time to prepare and train their System Operators.
Created2008-10-23
Approved2009-05-20
Sections Affected
3.14.222 Attachment D
Summary
This Nodal Protocol Revision Request (NPRR) changes the Black Start Service bids from a one year period to a two year period.
Timeline
-
Sep 23 '08
PRSFiled by John Dumas on behalf of the Reliability and Operations Subcommittee (ROS)
-
Oct 23 '08
PRS PRS MeetingPRSReferred Referred → TPTF“To refer NPRR157 to the Transition Plan Task Force (TPTF) for consideration.” — Passed→ PRS Consideration
-
Oct 27 '08
Listed without action at 1 meeting
- Feb 23 '09
-
Mar 19 '09
PRS PRS MeetingPRSRecommended for Approval Recommended for approval“To recommend approval of NPRR157 as submitted” — Passed→ PRS consider the Recommendation Report and Impact Analysis
-
Apr 23 '09
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC“To endorse and forward the PRS Recommendation Report and Impact Analysis for NPRR157 to TAC” — Passed→ TAC Consideration
-
May 7 '09
TAC TAC MeetingTACRecommended for Approval Recommended for approval“To recommend approval of NPRR157 as recommended by PRS” — Passed→ ERCOT Board
-
May 20 '09
BOARDEmail Vote / Unlisted MeetingBOARDApproved Recommended for approval“To approve NPRR157 as recommended by TAC.” — Passed
-
—