ERCOT·WATCH Search ercot.com  ⌕
NPRR #156 · Revision Request

NPRR156  Transparency for PSS and Full Interconnection Studies

Approved sponsor Marguerite Wagner/PSEG Texas posted 2008-09-18 next action Consideration ercot.com
ReasonTo provide additional information for ERCOT and Market Participants related to generation equipment that affects stability limits and information about potential generation interconnections at the time a full interconnection study is requested.
Created2008-10-23
Approved2010-03-23
Sections Affected
1.3.1.1Items Considered Protected Information 1.3.1.2Items Not Considered Protected Information
Summary
Updates to Section 1 & 12 to provide transparency to status of Power System Stabilizer Equipment and interconnection requests.
Timeline