NPRR #151 · Revision Request
NPRR151 Clarify Definition of a Generator Output Breaker in the Outage Scheduler
ReasonDepending upon the configuration of the substation could result in reliability issues when the breakers that control generating unit output are left open indefinitely, and not reported in Outage Scheduler.
Created2008-09-24
Sections Affected
3.10.7.5.1Continuous Telemetry of the Status of Breakers and Switches
Summary
This Nodal Protocol Revision Request (NPRR) clarifies the definition of which "generator output breakers" are exempt in the Outage Scheduler.
Timeline
-
Sep 8 '08
PRSFiled by Anthony Alford w/ CenterPoint Energy
-
Sep 24 '08
PRS PRS MeetingPRSReferred Referred → TPTF Amended by the CPS Energy comments Amended by the Luminant comments“To refer NPRR151 to TPTF for review of CPS Energy’s and Luminant’s comments.” — Passed
- Oct 13 '08
- Feb 23 '09
- Mar 19 '09
- Apr 23 '09