NPRR #139 · Revision Request
NPRR139 ACL, EAL, FCE Calculation Updates
ReasonEliminate duplication with FCE component for establishing a forward value for CRR activity. Provide more flexibility for entities to prepay invoices Auction clearing price is as appropriate as the Hub price to replace a missing DAM Settlement Point Price and is more readily available Clarify the intent of the ACL.
Created2008-08-21
Approved2008-11-17
Sections Affected
16.11.4.3; 16.11.4.5; 16.11.4.6
Summary
Congestion Revenue Right’s (CRR’s) future exposure is represented by Future Credit Exposure (FCE) calculations. Including the CRR Invoices in Daily DA Liability Extrapolated (DALE) and Average Daily Transaction Extrapolated (ADTE) calculations result in calculating the future exposure more than once for CRR activity. Hence the CRR activity needs to be excluded from DALE and ADTE calculations. Eliminate the "two day" requirement for prepays. Invoices will be removed from the exposure calculation the day after they are paid. If the Day Ahead Market (DAM) is executed but specific DAM Settlement Point Prices are not available, ERCOT may use the appropriate auction clearing prices instead. 90% was mentioned twice, once in Available Credit Limit (ACL) definition and once in CRR auction credit limit. The intention is to apply 90% to ACL only once. Hence the 90% is removed from the ACL definition.
Timeline
-
Jul 11 '08
PRSFiled by Credit Working Group
-
Aug 21 '08
PRS PRS MeetingPRSReferred Referred → TPTF“To refer NPRR139 to Transition Plan Task Force (TPTF) for consideration.” — Passed→ PRS for consideration.
-
Aug 25 '08
Listed without action at 1 meeting
-
Sep 24 '08
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Amended by the TPTF comments“To recommend approval of NPRR139 as amended by TPTF comments.” — Passed→ PRS consideration of Impact Analysis
-
Oct 23 '08
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC“To endorse and forward the NPRR139 PRS Recommendation Report and Impact Analysis to TAC.” — Passed→ TAC for consideration.
-
Nov 6 '08
TAC TAC MeetingTACRecommended for Approval Recommended for approval“To recommend approval of NPRR139 as recommended by PRS.” — Passed→ Board consideration
-
Nov 17 '08
BOARDEmail Vote / Unlisted MeetingBOARDApproved Approved“To approve NPRR139 as recommended by TAC.” — Passed
-
—
Posted since the last meeting