NPRR #136 · Revision Request
NPRR136 Interim Solution for 15-Minute Settlement of Advanced Meters
ReasonAdvanced Metering Systems (AMS) will begin deployment after PUCT approval. Oncor and CenterPoint have filed AMS deployment plans (Docket numbers 35639 and 35718). Enabling settlement at ERCOT will allow the market to utilize the full value of these systems.When the PUCT commented on PRR 755, Demand Response Program, the Commissioners asked stakeholders to develop a demand response solution that utilized Advanced Meters. In addition, this NPRR was developed after full consensus was reached during Project 34610, Implementation Project Relating to Advanced Metering.
Created2008-07-17
Approved2008-11-17
Sections Affected
9.5.810.3.3.110.3.3.310.12.311.2.218.218.6.718.7.219.7 (new)
Summary
Implementing this Nodal Protocol Revision Request (NPRR) will support the interim settlement of all provisioned Advanced Meters using actual fifteen minute data, the same way Interval Data Recorder (IDR) meters are settled today, until the long-term solution developed by Project 34610, Implementation Project Relating to Advanced Metering, or future rulemakings is implemented.ERCOT and the Public Utility Commission of Texas (PUCT) have developed a Request for Information to investigate the long-term solution to advanced meter settlement and data transport. The PUCT unanimously approved the "Scope of Work" of the long-term study on May 22, 2008. See P.U.C. SUBST. R. 25.130(h), Advanced Metering.
Timeline
- Jun 20 '08
- Jul 7 '08
-
Jul 8 '08
Listed without action at 2 meetings (Jul 8 '08 – Jul 9 '08)
- Jul 17 '08
-
Jul 21 '08
Listed without action at 1 meeting
-
Sep 24 '08
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Amended by the Sep 8 '08 ERCOT comments Action“To recommend approval of NPRR136 as amended by ERCOT comments posted 9/08/08, and to change the status of NPRR136 to "Needed for Go-Live."” — Passed→ PRS consideration of Impact Analysis
- Oct 13 '08
-
Oct 23 '08
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC“To endorse NPRR136 and forward the PRS Recommendation Report and Impact Analysis to TAC.” — Passed→ TAC for consideration.
-
Nov 6 '08
TAC TAC MeetingTACRecommended for Approval Recommended for approval“To recommend approval of NPRR136 as recommended by PRS.” — Passed→ Board consideration
-
Nov 17 '08
BOARDEmail Vote / Unlisted MeetingBOARDApproved Recommended for approval“To approve NPRR136 as recommended by TAC.” — Passed
-
—
Posted since the last meeting