ERCOT·WATCH Search ercot.com  ⌕
NPRR #133 · Revision Request

NPRR133  Addtion of PSSE Format

Approved sponsor ERCOT Staff posted 2008-05-16 next action Impact Analysis ercot.com
ReasonThe Common Information Model (CIM) format has not been extended to represent bus-branch type models. The Electric Power Research Institute (EPRI) does have an initiative underway to do so but results are not yet available.
Created2008-05-22
Approved2008-08-19
Sections Affected
3.10.2Annual Planning Modeland 3.10.3CRR Network Model
Summary
This Nodal Protocol Revision Request (NPRR) adds the requirement to post Annual Planning Models and Congestion Revenue Rights (CRR) Network Models in the Power System Simulator for Engineering (PSS/E)format.This NPRR also proposes non-substantive edits.
Timeline