NPRR #1319 · Revision Request
NPRR1319 Clarification to Seasonal Mothball Evaluation Process
ReasonStrategic Plan Objective 1
Created2026-01-14
Sections Affected
3.14.1.23.14.1.2.1 (new)3.14.1.2.1and 22E
Summary
This Nodal Protocol Revision Request (NPRR) clarifies ERCOT’s next steps after a Generation Resource proposal to be placed on seasonal mothball status has been evaluated. The current language in some cases requires ERCOT to prepare and post a Must-Run Alternative (MRA) “Request for Proposal” (RFP). Given that a request to seasonally mothball a Resource can be submitted as little as 90 days before the season begins, if ERCOT studies indicate a reliability concern of the seasonal mothball request, in most cases there is not enough time to effectively go through the MRA process and receive operational alternatives in a timely manner. This NPRR clarifies that ERCOT may, but is not required to, go through the MRA RFP process when it receives notice to place a unit on seasonal mothball status.
Timeline
- Dec 29 '25
-
Jan 14 '26
PRS PRS MeetingPRSDeferred/Tabled Tabled Referred → ROS Referred → WMS“to table NPRR1319 and refer the issue to ROS and WMS” — Passed→ Language Consideration
- Feb 4 '26
- Feb 5 '26
-
Feb 11 '26
Listed without action at 1 meeting
- Mar 4 '26
-
Mar 5 '26
Listed without action at 2 meetings (Mar 5 '26 – Mar 11 '26)
- Apr 1 '26
-
Apr 2 '26
Listed without action at 1 meeting
- Apr 15 '26
-
May 6 '26
Listed without action at 2 meetings (May 6 '26 – May 7 '26)
- Jun 4 '26
-
Jun 10 '26
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Amended by the Feb 25 '26 ERCOT comments“to recommend approval of NPRR1319 as amended by the 2/25/26 ERCOT comments” — Passed→ Impact Analysis Consideration
-
Jul 15 '26
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC“to endorse and forward to TAC the 6/10/26 PRS Report and 12/29/25 Impact Analysis for NPRR1319” — Passed→ Revision Request Consideration
- Jul 29 '26