NPRR #1316 · Revision Request
NPRR1316 Implement an Annual ERCOT RFI Process to Gather Information Related to Retirement and Mothballing Plans of Select Resources
ReasonGeneral system and/or process improvement(s)
Created2026-01-14
Approved2026-07-09
Sections Affected
1.3.1.13.10.6
Summary
This Nodal Protocol Revision Request (NPRR) adds an annual requirement for any Resource Entity that owns or operates a thermal generating unit that is identified by ERCOT, through the use of a screening model, to be at risk of being retired or mothballed, and which has not yet already been listed in a Notice of Suspension of Operations form, to respond a request for information from ERCOT. As part of the annual requirement, the Resource Entity will receive a request for information from ERCOT of public or non-public retirement or mothball plans, as well as likelihood of retirement or mothballing if there are no such public or non-public plans. As specified in the NPRR, a Resource Entity will have 30 days to respond to the request for information, and all responses provided will be considered Protected Information under Section 1.3.1.1, Items Considered Protected Information.
Timeline
- Dec 19 '25
-
Jan 14 '26
PRS PRS MeetingPRSDeferred/Tabled Tabled Referred → WMS“to table NPRR1316 and refer the issue to WMS” — Passed→ Language Consideration
- Feb 4 '26
- Feb 11 '26
-
Mar 4 '26
Listed without action at 2 meetings (Mar 4 '26 – Mar 11 '26)
- Apr 1 '26
-
Apr 15 '26
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Amended by the Apr 2 '26 WMS comments“to recommend approval of NPRR1316 as amended by the 4/2/26 WMS comments” — Passed→ Impact Analysis Consideration
-
May 6 '26
PRS PRS MeetingPRSRecommended for Approval Recommended for approval Forwarded → TAC“to endorse and forward to TAC the 4/15/26 PRS Report and 12/19/25 Impact Analysis for NPRR1316” — Passed→ Revision Request Consideration
-
May 13 '26
TAC Special TAC MeetingTACRecommended for Approval Recommended for approval“to recommend approval of NPRR1316 as recommended by PRS in the 5/6/26 PRS Report” — Passed→ Revision Request Consideration
- Jun 1 '26
-
Jun 2 '26
BOARDEmail Vote / Unlisted MeetingBOARDRecommended for Approval Recommended for approval“to recommend approval of NPRR1316 as recommended by TAC in the 5/13/26 TAC Report” — Passed→ Revision Request Consideration
-
Jul 9 '26
PUCTPUCTApproved Approved“to approve NPRR1316 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Protocols Adopted by the Independent Organization” — Passed
-
—
Posted since the last meeting