ERCOT·WATCH Search ercot.com  ⌕
NPRR #1307 · Revision Request

NPRR1307  Revised Definition of Mitigation Plan

Approved sponsor ERCOT posted 2025-11-13 ercot.com
ReasonGeneral system and/or process improvement(s)
Created2025-12-10
Approved2026-07-09
Sections Affected
2.1
Summary
This Nodal Protocol Revision Request (NPRR) adds the use of pre-contingency Load shed in certain conditions to the Mitigation Plan definition.
Timeline